Hospital Gambiran II Kediri USD 234 M Threatened mangkrak

Development megaproyek District General Hospital (Hospital) Gambiran II Kediri which are located on land formerly cash Pakunden Village, School District, City of Kediri threatened mangkrak. Because the local parliament to stop the funding.

"The issue of developing the project (Gambiran II FC, ed) tripped over legal problems. Finally in the discussion of Amendment to Articles of Finance (PAK) yesterday, Parliament recommends that the funding is stopped, pending the report the Audit Board (BPK)," said Chairman of Commission C DPRD Hadi Sucipto Kediri, on Thursday (02/10/2011).

Politicians from the Indonesian Democratic Party of Struggle (PDIP) explains, this year, actually the third year of development process Gambiran II Hospital. Hospital construction project (RS) are intended for the recipient community impact of cigarette smoke

Hospital Project Gambiran II FC will Multy years worked for three years (2009-2012). To accomplish this, the City Government (City Government) Kediri require a budget of Rp 234 billion. Currently the project has done 50 percent.

In the first year, the City Government of Kediri budgeted funds of Rp 18.7 billion for land acquisition process. The second year amounted to Rp 63 billion. Consisting of Rp 41 funds from the BHC and the remaining Rp 22 billion from the budget of Kediri.

In fact, earlier this year the parliament had approved the requested amount of funding municipal government amounted to Rp 39 billion Kediri. However, Hadi said, the fund was still intact. "This is a konskuensi, if the project is done tripped legal problems. The fund should be stopped," said Hadi.

Still said Hadi, Gambiran II Hospital construction project can proceed after the new FC BKP report states that the project is no problem. However, Hadi, reluctantly identifies the issue of legal problems that meant.

Based on the news, earlier, hospital construction projects Gambiran II FC is in the spotlight all walks of life, particularly Non-Governmental Organization (NGO).

NGOs concerned about the licensing process principles that have not been completed, the process of working that do not involve idependent team, and the placement location of buildings in the area not far from the extra Air Channel High Voltage (EHV transmission lines) that impact on health problems.